Highway improvement programme

Every year we undertake an annual capital programme to maintain carriageway (including cycleways) and footway / pavement surfaces throughout Trafford.

Works are identified for the annual programme based on a priority ranking system. This is in accordance with our Highways Infrastructure Asset Management Plan (HIAMP).

Properties and businesses potentially impacted by any schemes will receive relevant communication for all schemes in advance of works commencing.

Types of improvements

There are several different methods used to improve highways in Trafford. The selection of method depends on the condition of the carriageway or footway. These methods include, but are not limited to:

  • Surface (or preventative) treatment – material is laid over the top of the old highway surface It can extend the life of the road by up to 10 to 15 years and protects the structure from water ingress.
  • Resurfacing – some or all of the existing surface of the highway is removed and replaced by a new surface layer.
  • Reconstruction – some or all of the material below the surface of the highway is replaced to re-establish structural integrity. Resurfacing also takes place.

We may also carry out more localised patching schemes in addition to those schemes listed.

Carriageway resurfacing and reconstruction programme 2024-25

The listed resurfacing and reconstruction schemes are scheduled to take place during 2024-25. Weather conditions may impact start dates and times.

Carriageway resurfacing and reconstruction programme 2024-25
SchemeExtentsWardType of improvementForecasted startStatus

Banky Lane

Sub-section outside the wastewater treatment site

Bucklow-St. Martins

Resurfacing

Q3

Pending

Broomfield Lane

Junction with Grove Road to junction with Hale Road

Hale

Resurfacing

Q1

Pending

Bucklow Avenue

Full extents

Bucklow-St. Martins

Resurfacing

Q1

Pending

Cherry Lane

Junction with Ryfield Road to junction with Firs Way

Manor

Reconstruction and Resurfacing

TBC

Pending

Cloverley Drive

Junction with Wood Lane to junction with Drayton Grove

Hale Barns and Timperley South

Resurfacing

Q2

Pending

Haydock Drive

Full extents

Hale Barns and Timperley South

Resurfacing

Q2

Pending

Humphrey Crescent

Full extents

Stretford and Humphrey Park

Resurfacing

Q1

Pending

Lingfield Avenue

Number 40 – number 102

Manor

Resurfacing

Q1

Pending

Millway

Full extents

Hale Barns and Timperley South

Resurfacing

Q3

Pending

Newgate Road

Sub-sections

Manor

Resurfacing

TBC

Pending

Oakwood Lane

Sub-sections

Bowdon

Resurfacing

Q1

Pending

Park Road (Bowdon)

Pinewood to junction with Talbot Road

Bowdon

Resurfacing

TBC

Pending

Park Road (Timperley)

Westwood Avenue to junction with Brookfield Avenue

Timperley North

Resurfacing

Q1

Pending

Queens Road

Junction with Moss Lane to junction with Stamford Park Road

Hale

Resurfacing

Q2

Pending

Westinghouse Road

Sub-sections from junction with Warren Road to junction with Mosley Road

Gorse Hill and Cornbrook

Resurfacing

Q2

Pending

Surface treatment programme 2024-25

The listed surface treatment schemes are scheduled to take place during 2024-25. The list is subject to ongoing review as sites are assessed, and confirmed for suitability, by potential sub-contractors. Weather conditions may also impact start dates and times.

Surface treatment programme 2024-25
SchemeExtentsWardType of improvementForecasted startStatus

Alderley Road

Junction with Frodsham Road to junction with Chelford Road

Sale Moor

Surface Treatment

Q2

Pending

Bradwell Avenue

Junction with Ashbourne Road to cul-de-sac end

Lostock and Barton

Surface Treatment

Q2

Pending

Bridgewater Street

Full extents

Sale Central

Surface Treatment

Q2

Pending

Brighton Grove

Full extents

Ashton upon Mersey

Surface Treatment

Q2

Pending

Brooks Road

Full extents

Old Trafford

Surface Treatment

Q2

Pending

Byron Road

Full extents

Gorse Hill and Cornbrook

Surface Treatment

Q2

Pending

Chinley Avenue

Full extents

Lostock and Barton

Surface Treatment

Q2

Pending

Crofton Street

Full extents

Old Trafford

Surface Treatment

Q2

Pending

Derbyshire Road

Junction with Marsland Road to junction with Alexandra Road

Brooklands

Surface Treatment

Q2

Pending

Gatley Road

Full extents

Sale Moor

Surface Treatment

Q2

Pending

Haddon Grove

Full extents

Sale Central

Surface Treatment

Q2

Pending

Kelsall Street / Springfield Road

Full extents

Sale Central

Surface Treatment

Q2

Pending

Kendal Avenue

Full extents

Brooklands

Surface Treatment

Q2

Pending

Khartoum Street

Full extents

Old Trafford

Surface Treatment

Q2

Pending

Kingston Drive

Full extents

Sale Central

Surface Treatment

Q2

Pending

Kirkby Avenue

Full extents

Brooklands

Surface Treatment

Q2

Pending

Lee Crescent

Full extents

Longford

Surface Treatment

Q2

Pending

Lilian Street

Full extents

Old Trafford

Surface Treatment

Q2

Pending

Lincoln Avenue

Full extents

Lostock and Barton

Surface Treatment

Q2

Pending

Longford Road

Full extents

Gorse Hill and Cornbrook

Surface Treatment

Q2

Pending

Lurgan Avenue

Full extents

Brooklands

Surface Treatment

Q2

Pending

Marple Grove

Full extents

Gorse Hill and Cornbrook

Surface Treatment

Q2

Pending

Priory Road

Full extents

Sale Central

Surface Treatment

Q2

Pending

Pulford Road

Full extents

Brooklands

Surface Treatment

Q2

Pending

Strathmere Avenue

Full extents

Gorse Hill and Cornbrook

Surface Treatment

Q2

Pending

Winston Close

Full extents

Ashton upon Mersey

Surface Treatment

Q2

Pending

Footway programme 2024-25

We are in the process of confirming the footway programme for 2024-25 and will update this page in due course.