Timescales for the project

Part of: Carrington Relief Road

Following Executive Board approval of Route F in September 2021, work has been underway to understand the area, the potential environmental impacts of the scheme and developing the design for the relief road.

Consultation on the proposals was undertaken in January and February 2025. Following this, the feedback was reviewed. A planning application for the Carrington Relief Road was submitted in December 2025.

Visit the Carrington Relief Road website for further information.

Key stages Anticipated date 
planning application determination expected Mid 2026
Start of construction Spring 2030
Construction completed Summer 2032

If you have any queries you can email us at carringtonrr@amey.co.uk.