Once you have checked you meet all of the required criteria outlined in step 1, you can request an assessment.
A deposit of £60.38 is required for an assessment. This fee covers the cost of administration and a site assessment by a member of the highways team.
Should approval be given, and you choose us to complete the work, this deposit will be deducted from your final cost.
Next steps
Upon receipt of an application and payment of a deposit, a member of the highways team will visit the property to assess the site, and individually price your application.
The cost will vary depending on the size and complexity of the required crossing to suit your property.
We aim for such assessments to be completed within 4 weeks of receiving your application. Should your application be approved, and you want us to carry out the works, they should be completed within eight weeks.
We will advise of a commencement date at least 24 hours before the works are due to start. However, delays may still occur at short notice due to unforeseen circumstances.