Previous schemes

Part of: SEND capital projects

2022 schemes

School Scheme Update
Brentwood School (secondary) Expansion for increasing cohort size. Additional capacity for 80 places (increase from 45 additional places) to meet needs of secondary age children Building work currently on site and due to complete September 2025
Egerton School (secondary) Creation of new 6th form facility Works complete Summer 2023
Longford Park School (primary SEMH special school) Further 2 classrooms to create additional capacity for 16 places to meet needs of primary age children who present with SEMH/ASC/social communication needs and behaviour that challenges Works complete Autumn 2023
Primary School in North Additional small specialist class required for 20 pupils across key stages 1 and 2 for pupils with a range of complex needs. Partner School withdrew. Second EOI round in March 2024.
Primary School in Central Additional small specialist class required for 20 pupils across key stages 1 and 2 for pupils with a range of complex needs. Partner School withdrew. Second EOI round in March 2024.

2021 schemes

2021 schemes
Provision Scheme Funding request Status
Well Green Primary Accessibility requirements for pupils Nil from HNPCA Works complete Summer 2022 from other LA funding
Moss Park Infant SSC - new area for pupils with EHC £10,000 Complete
Longford Park Sensory area £10,000 Complete
Pictor Outdoor area £40,000 Complete
Flixton Girls Alt Prov for girls £35,000 Complete
Lime Tree Primary EOI – SSC for EYFS, KS1 & KS2 Nil Not taken forward in 2021
Trafford Alt Educ Gym & sensory space £31,500 Complete
Springfield Primary 1:1 pod spaces £5,000 Complete
Lostock High Outdoor area £35,000 Complete
Barton Clough Primary WC refurb for SSC pupils £15,000 Complete
Lime Tree Primary Accessibility for pupil – alterations to pathway £9,500 Complete
Seymour Park Primary Outdoor area £50,000 Complete
Wellacre Academy Accessibility for pupil – installation of closomat £6,930 Complete
Wellington Sensory garden £2,000 Complete
Heyes Lane Primary Outdoor area £3,000 Complete
Gorse Hill Studios Music studio £50,000 Complete
Wellfield Infant EOI – increase in SSC Nil Not taken forward in 2021
Delamere 1:1 learning pod £10,800 Complete

2021 Emergency measures

2021 Emergency measures
Provision Scheme Funding request Status
Brentwood School Adaptation of 2 spaces to create additional capacity for increase in Year 7 cohort. £44,000 Complete
Delamere School Individualised learning space for child who require low stimulating environment and high adult support throughout the school day £60,000 Complete
High Needs Services Robots to support remote access to the classroom £16,500 Complete

2019 schemes

2019 schemes
School Scheme Update
Lostock High School Expansion to existing provision supporting autism spectrum and social communication needs in a mainstream secondary school for between 10 to 15 pupils per class. With additional support from Educational Psychology, Speech and Language Therapy, Occupational Therapy and Healthy Young Minds. Works to be completed over Summer 2021
Egerton School Increase provision from 56 to 65 places by September 2020 Provision of mobile accommodation to support increase in pupil numbers. The additional accommodation will allow School to develop a fitness suite and further therapy suite. Works completed over Summer 2020
Manor Academy Increase provision by 25 places, including a change in the sixth form age range to include a third year (age 16-19) Redevelopment of co-located Sale West Conference Centre into 4 classrooms to allow multi-use of this area and support increase in pupil numbers and age range. Works completed November 2019

2018 schemes

2018 schemes
School Scheme Update
Secondary New class supporting autism spectrum and social communication needs in mainstream secondary schools for between 10 to 15 pupils per class. With additional support from Educational Psychology, Speech and Language Therapy, Occupational Therapy and Healthy Young Minds. Provision opened at Lostock High School in September 2018
Egerton School Provide a nurture class and outdoor area for year 7 and 8 pupils to help with their transition. Provision opened in September 2018
Delamere School Provision of toilets to support the needs of ambulant pupils as the geographical primary special school model takes effect. Works completed over summer 2018
Pictor Academy Provision of hoists in both key stages 1 and 2 to support the needs of non-ambulant pupils as the geographical primary special school model takes effect. Works completed in key stage 1 in 2018 and key stage 2 in 2019
Moorlands Junior Improvements to existing small specialist class to support social communication. Works completed over summer and autumn 2018
Delamere School Refurbishment and enlargement of hydrotherapy pool to meet the needs of all pupils at the school. New larger pool completed in January 2021

2018 bidding round

018 bidding round
Provision Scheme Funding request Status
Wellfield Junior School Creation of a small lobby area, for use as a quiet area to work as well as improving the security of the small specialist class. £5,000 Successful
Broomwood Primary School Creation of a multi-sensory area within the pre-school. £10,000 Successful
Longford Park School Creation of a multi-use games area. £130,000-£160,000 Partly Successful £80,000 awarded
Longford Park School Building adaptations (£15,000) and extension (£60,000) £75,000 Partly Successful £15,000 awarded
Gorse Hill Studios Improvements to access and music provision £50,000 Unsuccessful Revised bid received February 2019 was successful